News and developments
Contracts of work and the burden of proof
Introduction
In the case Aretrop Limited (C49725) (the “Claimant Company”) vs Foundation for Tomorrow’s Schools (the “Foundation”) & the Hon. Dr. Justyne Caruana in her capacity as Education Minister (the “Hon. Minister”), the Hon. Madame Justice Audrey Demicoli delved into and examined various contracts entered into between the parties for works carried out by the Claimant Company, including the delivery of specialised furniture in various schools around Malta and Gozo. This case was decided by the First Hall Civil Court (the “FHCC”) on the 6 June 2024.
The claimant company requested the FHCC (i) to determine whether the defendants or any of them were debtors of the Claimant Company for works carried out by the Claimant Company on the instructions of the defendants (ii) to liquidate the amount owed to the Claimant Company and (iii) order the defendants to pay the amount as liquidated.
Relevant Facts of the Case
The parties entered into six contracts between June 2019 and September 2020 for (i) the supply of furniture which the Claimant Company provided in various schools around Malta and Gozo; (ii) finishing and coating works at Valletta Primary School and (iii) the construction of a new substation in Birgu. These contracts, according to the Claimant Company, amounted to €159,857.89.
The relevant contracts were the following:
Contract A: Furniture for the Principal’s Office at St. Thomas More College, St. Lucija Secondary School
Contract B: Furniture for Sannat Primary School, Gozo
Contract C: Plastering and painting at Valletta Primary School
Contract D: Furniture for VET labs for various State Secondary Schools
Contract E: Furniture for VET Labs Gozo & Dingli Secondary Schools
Contract F: Construction of a sub-station using Environmentally Friendly Products at Birgu Fortini School (Malta)
During the course of the proceedings, 3 schedules of deposits were filed in Court in the amount of €34,697.77, thereby reducing the amount allegedly owed to the Claimant Company to €125,224.52.
Defendants’ pleas
The Foundation, in its Sworn Reply, held that:
The Hon. Minister, in her sworn reply held that:
Courts Considerations
The FHCC first went on to examine the defendants’ preliminary pleas:
The FHCC then went into the merits and examined each contract in detail:
Contract A: The amount relative to this contract was that of €3,720.46. However, given that a Schedule of Deposit was filed in court in this exact amount, the court held that this amount was no longer due.
Contract B: The amount relative to this contract was €1,079.38. However, the Foundation claimed that the amount due was €950. Given that no proof was brought by neither the Claimant Company nor the Foundation as to which of the two amounts was owed, the court considered that the amount was no longer due.
Contract C: The amount relative to this contract was €7,532.46. A Schedule of Deposit was filed in court in the amount of €7,418.05, and therefore there was a discrepancy of €114.41. Given that evidence to account for the difference in amounts was not provide by the Foundation, the court declared that this amount was still due.
Contract D: The amount relative to this contract was €76,188.32. The global amount for furniture delivered by the Claimant Company was €265,932.59. However, the Foundation claims that the global amount is €219,009.55. The FHCC had to first determine which of the two amounts was correct. Under this contract, the Foundation claimed that a number of defects were present in the furniture delivered, and that the furniture was not of the agreed quality. The Claimant Company thus held that the Foundation cannot expect to not pay for goods which were already delivered and made use of. In view of this, it certainly could not be held that the defect was not visible or that the Foundation could claim, 2 years after delivery, that the tables delivered were in fact defected. The FHCC thus declared that the amount due under this contract was €36,830.
Contract E: The amount relative to this contract was €9,842.69. Given that the Foundation had made 3 payments totalling to €46,230.57, which amount included the €5,766.99 filed by means of a Schedule of Deposit, the FHCC declared that the amount due under this contract was in the amount of €4,598.24.
Contract F: The amount relative to this contract was €61,494.38. Although the Foundation, did not bring any evidence to show that the amounts were not due, it did hold that part of the payment could not be made given that the necessary approvals were still pending. The FHCC held that it was for the Foundation to request such authorisation and that the Claimant Company should not have to suffer for a failure on the part of the Foundation. The FHCC thus declared that the amount due under this contract was €54,649.24.
Decision
In conclusion and for the above-mentioned reasons, the FHCC declared that the Foundation was in fact a debtor of the Claimant Company in the amount of €96,191.89 in representation of various work carried out by the Claimant Company on the instructions of the Foundation, including the sale and delivery of specialised furniture in various schools across Malta and Gozo.
Disclaimer: Ganado Advocates is responsible for contributing to this law report but was not in any way involved as legal advisor for the parties in the judgement being covered in this law report. This article was first published in The Malta Independent on 26/06/2024.
Author: Krista Refalo
Footnotes
[1] 2148. The following actions are barred by the lapse of eighteen months: